Construction sequence and erection
A substation is built in stages, and each stage needs the work of the one before it. The site is cleared and levelled, the soil is investigated, and the foundations, trenches and earth mat are laid. The structures go up next, and the equipment is erected on them and wired. The yard is then surfaced, tested and inspected before it is energised. This topic explains the stages and what each one takes from the design. It closes with the drawings and the bill of materials (BOM) that the design gives the builder, and with the work the design leaves to the construction drawings.
Before this topic: Yard layout · Roads, trenches and buildings · Bill of materials
1The stages of construction
Construction turns the design's drawings into a working substation, so its order follows the dependencies between the trades. A structure needs its foundation, a breaker needs its structure, and a cable needs both its ends in place. RUS Bulletin 1724E-300 lists the chronology of a substation project in its Table 3-1. Its later steps are the selection of a construction contractor, construction, inspection, testing and energising (RUS 1724E-300 §3.3). The design and the specifications come before them, because the contractor builds from formal plans.
The primary function of a substation design engineer is to produce the formal plans from which a substation can be constructed (RUS 1724E-300 §3.1). The work on site starts only when those plans exist. Figure 1 shows the stages of the work and the design documents each one draws on. The order inside a stage is the contractor's. A utility's specification requires the contractor to submit a detailed programme to the site in-charge, in line with the outline programme of the bidding documents (OPTCL Technical Specification E-6 §25.0).
2Site clearance, survey and levelling
The first work on site removes what stands in the way of the yard. Clearing and grubbing removes trees, bushes, roots, rubbish and other unsuitable material. It is done in advance of the earthwork, with precautions against soil erosion and water pollution (OPTCL E-6 §2.1). The contractor then sets out the limits of the excavation, establishes bench marks and fixes a grid of coordinates on the site (OPTCL E-6 §2.2). The grid ties the positions of the foundations on the yard plan to points on the ground.
The yard is then levelled to its formation level. The contractor cuts the soil where it stands above that level, uses the usable soil as fill, and brings in borrowed earth where the cut soil is not enough (OPTCL E-6 §7.0). RUS 1724E-300 gives the method for balancing the two. The nominal elevation of the yard is usually set by a balance between the fill the embankment needs and the earth cut from higher areas (RUS 1724E-300 §6.5.3). Only 80 to 85 % of the cut volume is assumed to be available as fill. The remaining 15 to 20 % allows for compaction, spillage and unsuitable material. Topsoil is generally stripped and stockpiled for areas that will be seeded (RUS 1724E-300 §6.5).
The site design rests on survey data gathered before the work. RUS 1724E-300 §6.3 lists the information: area maps, a topographic drawing with ground elevations on a grid, the location of existing utilities and drainage exits, the flood level and soil borings.
3Soil investigation
The design takes 2 properties of the soil, and both are measured on site before the foundations are built. The first is its strength. Foundation design depends primarily on the in-place density and the strength and strain properties of the soil (RUS 1724E-300 §8.1). The design of a foundation addresses the allowable bearing capacity of the soil and the allowable deformation of the structure under load. These values come from site borings and laboratory tests, which a geotechnical engineer interprets.
The second property is the soil's resistivity, which sets the size of the earth mat. A utility's civil specification includes the measurement of soil resistivity in the contractor's scope, with the method of the code of practice for earthing. The value it yields is taken for the design of the earth mat (OPTCL E-6 §4). Soil resistivity and Wenner readings, The Wenner method explains the Wenner method and how the design value is drawn from the readings. A mat designed on a resistivity that differs from the site's gives touch and step voltages that differ from the calculated ones, so the measurement belongs before the mat is ordered.
4Foundations, trenches and the earth mat
The civil works below ground are built together, because they share the same excavated yard. A utility's civil scope covers the foundations of the switchyard structures, the gantries and the equipment supports, and the cable trenches with their covers. It also covers the marshalling box foundations, the transformer foundations, the firewalls and the control building (OPTCL E-6 §1.1). The foundations are of reinforced cement concrete. No concrete is placed in a foundation until the site in-charge has passed its excavation (OPTCL E-6 Part B, Section I §1.5).
The earth mat is laid in the same period, at its own depth and around the other works. In a transmission utility's switchyard specification, the employer gives the spacing of the main earth mat, and the contractor prepares the mat's layout drawings from it. The main earth mat is then laid in the switchyard area in accordance with its layout drawings (POWERGRID switchyard erection specification §9.1). Its outdoor conductors are buried at least 600 mm below the finished ground level (POWERGRID switchyard erection specification §9.5.1). Where a conductor crosses a cable trench, duct or pipe, it is laid at least 300 mm below it. It is routed around an equipment or structure foundation that it would otherwise meet (POWERGRID switchyard erection specification §9.5.2).
The same specification places the conductor around a building at least 1500 mm from the building's outer boundary (POWERGRID switchyard erection specification §9.5.5). The tap connections from the mat to the equipment and the structures end on the earthing terminals of each item (POWERGRID switchyard erection specification §9.5.3). The contractor also measures the resistivity of the stone for the surface layer (POWERGRID switchyard erection specification §9.1). The measurement checks the value assumed in the mat's design, and with it the tolerable touch and step voltages of Surface layer and Cs.
5Structures and gantries
The structures carry the equipment, the buses and the incoming lines, and they stand on the finished foundations. They are of galvanised steel lattice or tubular members, bolted to anchor bolts cast into the foundations. RUS 1724E-300 §3.5.2.2 specifies that tolerances be noted on drawings that give the locations of foundation anchor bolts, since the structure must fit them.
Erection loads are part of the structure's design. RUS 1724E-300 §7.4.9 recommends that the designer consider construction loads, such as the pulling and hoisting of equipment into place. Such loads do not usually govern the design, but they are evaluated. A line gantry also takes the tension of the incoming conductors and shield wires once they are strung.
The structures carry the phase identification of the yard. A transmission utility's specification paints a colour band of red, yellow or blue around the top of each phase's structure, at a height of approximately 2000 mm above the finished ground level (POWERGRID switchyard erection specification §11.4.2). It also fixes a name plate on each bay to its standard drawing (POWERGRID switchyard erection specification §11.4.1).
6Equipment erection
The equipment is erected on its structures to the manufacturers' instructions. In a transmission utility's specification, the erection of the circuit breakers and the isolators (disconnectors, IEC 60050) is done under the supervision of the equipment manufacturer. The erection of the switchyard equipment follows the utility's field quality plan (POWERGRID switchyard erection specification §13.1). A field quality plan is the programme of the inspections and tests of the field work, from the receipt of the material to commissioning. The contractor prepares it with the manufacturer, and the purchaser accepts it (CEA standard specification for transformers and reactors, Ch. 5 §11.0).
Several of the specification's rules protect the equipment's contacts and insulators. The terminal pads, tubes, conductors and clamps are cleaned, and contact grease is applied before the bolts are tightened (POWERGRID switchyard erection specification §13.2). Support insulators, breaker interrupters and other fragile items are handled with cranes of suitable boom and capacity (POWERGRID switchyard erection specification §13.4). Slings are long enough to avoid excessive swing or scratching of the insulators (POWERGRID switchyard erection specification §13.9).
A power transformer is the largest single item and has a sequence of its own. The CEA standard specification for transformers and reactors makes the supplier responsible for the route survey and the transport. The unit travels on multi-axle low platform trailers fitted with tracking (Ch. 5 §1.1 to §1.3). It is despatched filled with dry air at positive pressure. Its storage at site under dry air is preferably limited to 3 months, transport included (Ch. 5 §1.5). Power transformers, Transport explains why the transport limits the unit's size.
The specification's flow chart of the erection runs in this order (Ch. 5 §16.0):
- Verify the plinth and cooler bank foundations against the drawings, and receive and check the tank and accessories for damage, with the impact recorder's values analysed with the manufacturer.
- Place the main tank on its plinth, evacuate it and fill it with dry air, and inspect it internally.
- Erect the turrets with their current transformers (CTs), the bushings, the cooler banks, the conservator and the Buchholz relay.
- Evacuate the tank, check it for leaks and fill it with filtered oil under vacuum, then circulate the hot oil through the filter machine.
- Carry out the pre-commissioning checks and tests (Testing and commissioning of substation equipment, Commissioning and energisation).
7Cabling, surfacing and handover
The cables join the equipment to the marshalling kiosks and the control building, through the trenches built with the foundations. A utility's specification gives each bay a marshalling kiosk, which takes 2 incoming auxiliary supplies with auto changeover and distributes them to the bay's equipment (POWERGRID switchyard erection specification §11.2). The control and power cables run between these kiosks, the equipment and the panels of the control building.
The surface of the yard is finished after the erection. In a utility's civil specification, the site is compacted to its lines and grades after the structures and equipment have been erected and accepted. The soil has an anti-weed treatment first (OPTCL E-6 §8.2(d)). Plain cement concrete 75 mm thick is laid next, with holes for drainage (§8.2(f)). A base layer of gravel and a final surface course follow, each of at least 50 mm of 20 mm nominal size, extending 2 m beyond the fence (§8.2(g), §8.2(h)).
The last stages are testing, inspection and energisation, which Testing and commissioning of substation equipment explains. In the IEC + CEA / CBIP set, an installation above the voltage that the government notifies is inspected and tested by the Electrical Inspector before supply commences (CEA Safety Regulations 2023, Reg. 45(3)). The supplier may energise the lines and apparatus for the site tests (Reg. 45(4)). In the ANSI / IEEE set, RUS 1724E-300 places inspection, testing and energising after construction in its chronology (§3.3, Table 3-1).
8In the design
SubstationLayout plans no construction: it sets no programme, designs no foundation and routes no cable. It gives the builder the drawings and the quantities that the stages of Figure 1 build from. RUS 1724E-300 §3.5.3 lists the drawings a substation's construction often requires, from the one-line diagram, the plot plan and the grounding layout to the foundation and conduit layouts. The design draws the first part of that list.
Drawings. The default project's drawings carry their numbers: the single-line diagram SSL-E-SLD-001, the electrical key diagram SSL-E-EKD-001 and the yard plan and sections SSL-E-LAY-001. The earth mat layout is SSL-E-EAR-001, with its typical details SSL-E-EAR-002. The lightning protection drawing is SSL-E-DSL-001, and the auxiliary supply diagram is SSL-E-AUX-001. The yard drawing's notes state that its equipment footprints are indicative and are finalised with the vendors' general arrangement drawings. They also state that cable trenches are not covered by the drawing set.
Earth mat. The earth mat drawing gives the conductor, its depth and the electrodes. The default project's mat is of 40 mm diameter, buried at 0.6 m, 11 736 m in all, with 150 electrodes of 40 mm × 3 m (Conductor sizing).
Structures. The BOM's Structures section counts the steel that stage 4 erects. The default project has 1 line gantry, 10 shield-wire towers or gantry peaks, 32 equipment support structures, 39 isolator support structures and 54 bus post insulator supports. It estimates 150.7 t of galvanised structural steel from typical weights per structure (Bill of materials, Structure steel).
Civil works. The BOM's Civil section gives 3165 m² of roads, 633 m of fence and 2589 m³ of gravel at 0.1 m thick. The control and switchgear building has a floor area of 648 m² (Roads, trenches and buildings, Example 1). The yard plan places the transformers' soak pits 1.5 m beyond each tank, and a firewall where 2 transformers stand closer than 10 m (Roads, trenches and buildings, Transformer pits and firewalls).
Before energisation. The compliance checklist of the IEC + CEA / CBIP set has an item for the electrical inspector's consent to energise the installation (CEA Safety Regulations 2023, Reg. 45(3), 45(4)). The item has no automatic check, and it reads Needs your answer until the user answers it.
- List the stages of a substation's construction in their order.
Answer 1
Site clearance, survey and levelling; soil investigation; foundations, trenches and the earth mat; structures; equipment erection; cabling; testing, surfacing and inspection; energisation (The stages of construction).
- Explain why only part of the cut volume counts as fill when the yard is levelled.
Answer 2
RUS 1724E-300 assumes only 80 to 85 % of the cut volume is available for fill, allowing for compaction, spillage and unsuitable material (Site clearance, survey and levelling).
- State how the earth mat is laid where it meets a cable trench or a foundation.
Answer 3
It is laid at least 300 mm below a trench, duct or pipe that it crosses, and routed around a foundation that it would otherwise meet (Foundations, trenches and the earth mat).
- Describe the order in which a power transformer is erected on site.
Answer 4
The foundations are verified and the unit received and checked, the tank placed and inspected, the turrets, bushings, coolers and conservator erected, and the tank filled with oil under vacuum before the pre-commissioning tests (Equipment erection).
- Name the drawings that the design gives the builder of the default project.
Answer 5
The single-line diagram, the electrical key diagram, the yard plan and sections, the earth mat layout and its typical details, the lightning protection drawing and the auxiliary supply diagram (In the design).
[1]RUS Bulletin 1724E-300, Design Guide for Rural Substations.
[2]OPTCL Technical Specification E-6, Technical Specification E-6, Civil Works.
[3]POWERGRID switchyard erection specification, Technical Specification, Section: Switchyard Erection.
[4]CEA standard specification for transformers and reactors, Standard Specifications and Technical Parameters for Transformers and Reactors (66 kV & above voltage class).
[5]CEA Safety Regulations 2023, Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023.
[6]IEC 60050-441, International Electrotechnical Vocabulary, Part 441: Switchgear, controlgear and fuses.
Reference topics explain the methods of the standards for study. For a design, apply the standards and regulations in force.