Operation and maintenance

A substation in service is kept safe and available by its operation and its maintenance. Operation switches the circuits in and out of service, and maintenance keeps the equipment in a condition to do its duty. Both depend on records, because the condition of a piece of equipment is read from the trend of its tests. This topic explains the strategies of maintenance and the main inspections and tests in service: thermography, dissolved gas analysis of transformer oil, the counting of breaker operations and the testing of the earth mat. It closes with the switching operations and the permit to work that make a circuit safe for the people who work on it.

Before this topic: Testing and commissioning of substation equipment · Interlocking between the devices of a bay

1The duties of operation and maintenance

The owner of an installation above 650 V maintains and operates it in a condition free from danger, as the manufacturer or the relevant standards recommend (CEA Safety Regulations 2023, Reg. 48(7)). The apparatus, cables and supply lines are maintained in healthy condition, and tests are carried out periodically as per the relevant standards (Reg. 48(5)). These are the duties of the IEC + CEA / CBIP set. In the ANSI / IEEE set, RUS Bulletin 1724E-300 gives the same work in its chapters on inspection, tests and maintenance, tailored to each site and its equipment (RUS 1724E-300 §18.1).

Records join the tests of different years into a history. The records of the tests, trippings, maintenance works and repairs are kept so that they can be compared with past records (CEA Safety Regulations 2023, Reg. 48(6)). RUS 1724E-300 keeps a record system for each substation, with the equipment's nameplate data, the inspection records and an inspection checklist for the site (§18.2.1). The failure of a transformer, a reactor or a transmission line tower at 220 kV and above is reported to the Authority within 48 hours. Its causes and the measures against a recurrence are sent within 1 month of the failure (CEA Safety Regulations 2023, Reg. 48(8)).

Maintenance begins in the design. A substation's design allows maintenance with a minimum impact on its operation, and allocates adequate working space for it (RUS 1724E-300 §2.8). The choice of the bus scheme, the clearances and the access roads determines which circuits stay in service while one is maintained.

2Maintenance strategies

The strategies differ in what starts a maintenance task. Time-based maintenance carries out preventive maintenance at predefined intervals. Corrective maintenance repairs equipment after it fails. Condition-based maintenance acts on the measured condition of the equipment, and reliability-centred maintenance (RCM) adds the consequences of a failure (CEA standard specification for transformers and reactors, Ch. 6 §1.0). The CEA specification observes that equipment reliability is compromised as the interval of time-based maintenance is increased. It names condition-based maintenance as the option that overcomes this shortcoming.

Condition monitoring is the process of monitoring a parameter of the equipment to identify a significant change that indicates a developing fault (CEA specification Ch. 6 §1.0). It can be continuous or temporary, online or offline. Online monitoring supervises the equipment continuously and avoids errors of sampling. The CEA specification lists the benefits of condition-based maintenance as advance information for planning an overhaul, fewer forced outages and information for assessing the remaining life.

RCM is a structured process that identifies the effects of failures and defines the maintenance path for managing their impacts. It weighs an asset's operating time and condition, its position in the network, its operational importance and the safety and environmental risks of its failure (CEA specification Ch. 6 §1.0). A criticality index is usually combined with a health index to rank the maintenance. An important transformer serving many consumers may need more maintenance than one with a backup unit. RUS 1724E-300 names 4 methods of maintenance within RCM: corrective, preventive, proactive and predictive (§20.4.1). It adjusts an interval by age exploration. An interval is lengthened by 10 % while no degradation appears, then shortened by 10 % once it does, and that becomes the task's interval.

The ANSI / IEEE set's sources move from fixed intervals towards the condition. RUS 1724E-300 §20.2 observes that maintenance at the frequency the manufacturers recommend can exceed what the equipment's condition needs, and can lead to more failures of equipment that would otherwise be functional. It recommends that utilities look for ways to maintain on the actual condition. The Bureau of Reclamation's volume on the maintenance of power circuit breakers, FIST 3-16, finds condition-based maintenance warranted for medium-voltage and high-voltage breakers. An overhaul is then made when the components are worn, before the breaker fails (FIST 3-16 §1.3).

3Inspections in service

Inspection is the first source of the condition. RUS 1724E-300 recommends a visual inspection of the whole substation monthly, an inspection with online diagnostic equipment annually and a detailed inspection of the major equipment annually. It recommends an internal inspection of transformers as required, and allows the frequencies to change under an RCM programme (RUS 1724E-300 §18.3). The visual inspection is made with the substation energised, so it is made from ground level, with binoculars for the buses and equipment on structures (RUS 1724E-300 §18.3.1).

The visual inspection of a power transformer looks at its control cabinet, its bushings and terminals, its oil leaks and its oil levels in the tank, the tap changer compartment and the bushings. It also reads and records the operations counter of the load tap changer and observes the oil temperature (RUS 1724E-300 §18.3.1.1). FIST 4-1B adds a check of the gauges themselves. A temperature, pressure or oil level gauge that does not vary with the seasons and the load is suspect (FIST 4-1B §34.4.2; FIST 3-30 §4.1.8).

The inspection of the earthing, whose tests Earthing in service covers, needs care. A gap in a ground connection can carry a high voltage, particularly under a fault. A ground connection is therefore not removed for any reason while the substation is energised (RUS 1724E-300 §18.3.1).

4Infrared thermography

A loose or corroded connection carrying load runs hotter than the conductors around it. Infrared thermography detects this from a distance, while the equipment is energised. The infrared camera shows an image of the infrared energy emitted by the objects in its view, so a hot spot appears as a temperature difference from the surrounding conductors (RUS 1724E-300 §18.3.2.1). The scan is made at the maximum possible load, and not below 40 % of the rated load of the equipment. The camera detects a difference of 1 °C at 30 °C (RUS 1724E-300 §18.3.2.1).

RUS 1724E-300 grades a hot spot by its difference from a reference area. A difference of 1 °C to 2 °C indicates a possible deficiency that warrants investigation. A difference of 4 °C to 15 °C indicates a deficiency that is repaired as time permits. A difference of 16 °C and above indicates a major deficiency that is repaired immediately (RUS 1724E-300 §18.3.2.1). The CEA specification grades a transformer's connections by their temperature rise above ambient (CEA specification Ch. 6 §2.16). A rise up to 10 °C is minor and repaired in the regular maintenance schedule. A rise from 11 °C to 39 °C is intermediate and repaired within 2 to 4 weeks. A rise from 40 °C to 75 °C is serious and repaired within 1 to 2 days, and a higher rise is critical and repaired immediately.

The 2 scales grade different quantities, a difference from a reference area and a rise above ambient, so a value of one is not read against the other scale. The scans are periodic. FIST 4-1B makes an infrared scan of sulphur hexafluoride (SF6) breakers and of surge arresters annually (FIST 4-1B §9.7, §3.2). FIST 3-30 scans a transformer's bushings, radiators and tank after 1 month of service and yearly (FIST 3-30 §3.2.5, §4.1.8).

5Dissolved gas analysis of transformer oil

A transformer's oil insulates and cools its windings, and it also dissolves the gases that the oil and the paper insulation produce as they degrade (FIST 3-30 §4.4.1). Dissolved gas analysis (DGA) extracts these gases from an oil sample and measures each in parts per million, by headspace extraction and gas chromatography (CEA specification Ch. 6 §2.11). The nature, amount and rate of generation of the gases indicate the type and degree of the abnormality that produced them. FIST 3-30 calls a DGA by far the most important tool for determining a transformer's health (§4.4.2).

The gases point to their source. Hydrogen, methane, ethane, ethylene and acetylene form from the degradation of the oil itself. Carbon monoxide, carbon dioxide and oxygen form from the degradation of the cellulose insulation (FIST 3-30 §4.4.3). A low-energy event such as partial discharge produces hydrogen with traces of methane and ethane. A high-energy sustained arc can generate all the gases, acetylene included, which needs the most energy (FIST 3-30 §4.4.3). A poor connection or a bad tap changer contact raises ethane and ethylene, and possibly methane (FIST 3-30 §4.7.1).

A single analysis is seldom conclusive. Detection of a gas does not by itself give the status of the transformer's health, and some gases come from benign causes such as stray gassing, an earlier fault now inactive or normal ageing (CEA specification Ch. 6 §2.11). Each analysis is therefore compared with the earlier ones to find the trend and the rate of generation (FIST 3-30 §4.4.2). An analysis is unreliable on a transformer that is de-energised and cooled, on a new one, or within 1 to 2 weeks of continuous service after oil processing (FIST 3-30 §4.4.2).

The analyses follow a schedule. FIST 3-30 specifies a DGA after 1 month of service and once each year, and more often if a problem appears (§4.4.2). The CEA specification requires one before commissioning, at intervals in the first 3 months, and then at intervals of 6 months or as the trend requires (Ch. 5 §14.0). The interpretation methods of the IEEE and IEC guides provide only guidelines for an engineering judgement (CEA specification Ch. 6 §2.11).

6Circuit breakers: operations and overhaul

A breaker wears with its operations, and above all with its fault interruptions. Its inspection therefore reads and records the number of operations shown on its counter (RUS 1724E-300 §18.3.1.3). An SF6 breaker's inspection also records its gas pressure and the gas or tank temperature, and compares the pressure with the manufacturer's graph of pressure against temperature (FIST 3-16 §8.2.1). RUS 1724E-300 Table 20-1 makes the major overhaul of a breaker a function of the number and type of its operations.

FIST 3-16 sets out the 2 ways to time an overhaul. An overhaul is normally due when a specified number of operations or full-load fault interruptions, or a recommended interval, has passed. Under condition-based maintenance, the diagnostic tests decide it instead (FIST 3-16 §1.3). Timing and motion analysis assess the operating mechanism, and the contact resistance assesses the contacts (Testing and commissioning of substation equipment, Tests of a circuit breaker). A result outside the manufacturer's limits sends the breaker to repair, and a worsening trend plans an inspection before it gets there.

FIST 4-1B gives a schedule for medium-voltage and high-voltage SF6 breakers (FIST 4-1B §9.7). It makes the visual inspection, the gas analysis and the infrared scan annual. It sets 6 years for the preventive maintenance, the timing and motion analysis and the contact resistance test. It sets the internal inspection or overhaul at 15 years, 5000 operations or 3 high-current interruptions, or as the manufacturer recommends. A breaker that rarely operates can slow on its first trip, because its lubricant stiffens. FIST 3-16 therefore operates such breakers periodically, with 3 close-open operations (§2.2).

7Earthing in service

An earth mat corrodes and the soil around it dries, so its resistance is checked through its life. IS 3043 keeps records of the initial resistance of a substation's earth electrodes and of the later tests (IS 3043:1987 §34.4.1). It measures the earth resistance of a substation normally once a year. Local experience may justify a longer or shorter interval, but not less than once in 2 years (IS 3043:1987 §34.4.2). The connections to the electrodes are inspected periodically for their rigidity and other signs of deterioration (IS 3043:1987 §34.4.3).

In the IEC + CEA / CBIP set, the earthing system is tested for its resistance on a dry day during the dry season, not less than once a year (CEA Safety Regulations 2023, Reg. 50(8)). The test is the fall-of-potential test of Testing and commissioning of substation equipment, The earth mat: the fall-of-potential test.

In the ANSI / IEEE set, RUS 1724E-300 measures the overall grid resistance if it has not been measured for a number of years. The shield wire grounds and the neutral connections are disconnected for the measurement, so the whole substation is de-energised for it (RUS 1724E-300 §18.4.9). The value is compared with the earlier values, to verify that changes of the groundwater level or similar causes have not changed the mat (RUS 1724E-300 §19.3.20).

8Switching operations and the permit to work

Work on a circuit begins with switching operations that isolate and earth it. The devices of a bay operate in a fixed order: the breaker opens first, then the isolators (disconnectors, IEC 60050), and the earth switch closes last (Interlocking between the devices of a bay, The operating sequence of a bay). Interlocks hold that order, but they cannot alone prove that a line is dead, since a line can be live from its remote end (Interlocking between the devices of a bay, The earth switch and the line voltage). The procedures of operation and work therefore add a test of the voltage, earths at the point of work and a written permit.

The CEA Safety Regulations 2023 require that, before a conductor or apparatus is handled, it is discharged by earthing or other suitable means. It is also prevented from being charged accidentally while persons work on it (Reg. 21(1)). No person operates or maintains any part of an electrical plant unless designated for it and observing the precautions of Schedule I (Reg. 21(3)). For shutdown work and testing, Schedule I Part II sets these precautions, in its order:

  1. The engineer in charge identifies the hazards of the work and briefs the working group on them.
  2. The engineer obtains a permit to work from the operation in-charge, and ensures that the circuit is isolated from all sources of energy, de-energised and earthed.
  3. Local earths are fixed at the zone of work, and stay connected until the people and materials have moved to a safe zone and the permit is returned.
  4. The engineer confirms positively by suitable means that the circuit is dead before giving the workers clearance to approach it (Part II (6)).
  5. The workers keep a safe distance from the adjacent live circuits, and no crane, ladder or tool infringes it.

Figure 1 combines these precautions with the practice of the safety earths in IS 3043, which tests the circuit for voltage before the earths are applied (IS 3043:1987 §33.2). The confirmation of Part II (6) is a second check, made at the zone of work before the workers approach. The devices are restored in the reverse of their order of opening: the earth switch opens first, the isolators close next and the breaker closes last (Interlocking between the devices of a bay, The operating sequence of a bay).

Figure 1.The steps that take a circuit out of service for work under a permit and return it to service, combined from CEA Safety Regulations 2023 Schedule I Part II, IS 3043:1987 §33.2 and the operating sequence of a bay. The drawing is schematic and not to scale.

The schedule adds conditions on the people. No lone worker is allowed to work or test, and the supervising personnel do not leave the spot while work at height or testing is in progress. Where shutdown work lasts more than a day, the engineer inspects the earthing at the site each morning before the workers climb (Schedule I Part II, further precautions). A local earth removed for a test is removed only with the workers in the safe zone, and refixed before they approach the conductors again (Part II (5)).

IS 3043 gives the practice of the safety earths themselves. Before earthing leads are applied, the circuit is verified dead with a voltage indicator that is itself tested immediately before and after (IS 3043:1987 §33.2). The leads are first bolted to the permanent earthing system, then to the conductors, and they are removed in the reverse order. On switchgear, the phases of the section are short-circuited and earthed to the same system. Where a winding of a transformer could become live, the terminals of its windings are earthed, and a cable or capacitor is discharged and kept earthed while work is in progress (IS 3043:1987 §33.3). On an overhead line, a working earth is placed at each point of work, against the line being energised by induction from other lines (IS 3043:1987 §33.4).

In the ANSI / IEEE set, RUS 1724E-300 specifies that the personnel know the operating procedures of the substation, its protective and interlocking schemes and the proper use of equipment grounding techniques. They keep the minimum distances from energised equipment of the National Electrical Safety Code (NESC) and the safety regulations that the bulletin lists (RUS 1724E-300 §18.2.2). Temporary barriers isolate the equipment being worked on from the adjacent energised equipment (RUS 1724E-300 §20.1.2).

9In the design

SubstationLayout plans no operation or maintenance: it sets no maintenance interval, keeps no record and issues no permit. It does fix the parts of the substation that make maintenance possible with the rest in service, and it lists the related requirements on the compliance checklist.

Maintenance with a bus live. The default project's 220 kV double main bus lets one bus be maintained while the circuits run on the other (Bus schemes, Bus schemes of the IEC + CEA / CBIP set). The yard keeps the sectional clearance of 5.0 m between the nearest phases of the 2 buses for this (Electrical clearances, The clearances of a level). The CEA / Indian checklist has the item "Sectional clearance for maintenance with one bus live" (CEA Safety Regulations 2023, Reg. 46(2)(iii), Schedule V), which the design checks against the yard.

Earthing of a circuit. The bill of materials (BOM) lists 3 line and transformer isolators with an earth switch, which earths the isolated circuit (Isolators and earth switches, Earth switches). The key diagram tags these devices, and a switching sheet names them by these tags (Interlocking between the devices of a bay, In the design).

Safety items. The CEA / Indian checklist has an item for the danger boards, phase identification and maintenance earthing at each bay (CEA Safety Regulations 2023, Reg. 20, 21(1), 26). It has another for the insulating mats, first aid, shock-treatment chart and fire extinguishers in the control room (Reg. 21(5), 29, 30). These items have no automatic check, and each reads Needs your answer until the user answers it.

Spares. The BOM carries the mandatory spares, such as 1 spare pole of the high-voltage circuit breaker and 3 spare current transformers (Bill of materials, Spares).

Review questions
  1. Compare time-based and condition-based maintenance.
    Answer 1

    Time-based maintenance works at predefined intervals, while condition-based maintenance acts on the measured condition of the equipment, which avoids the loss of reliability of a longer fixed interval (Maintenance strategies).

  2. State the load at which an infrared scan is made in RUS 1724E-300.
    Answer 2

    At the maximum possible load, and not below 40 % of the rated load of the equipment (Infrared thermography).

  3. Name the gases that the degradation of a transformer's paper insulation produces.
    Answer 3

    Carbon monoxide, carbon dioxide and oxygen (Dissolved gas analysis of transformer oil).

  4. Give the overhaul criteria of FIST 4-1B for an SF6 breaker.
    Answer 4

    An internal inspection or overhaul at 15 years, 5000 operations or 3 high-current interruptions, or as the manufacturer recommends (Circuit breakers: operations and overhaul).

  5. State when the CEA Safety Regulations 2023 require the earthing system's resistance to be tested.
    Answer 5

    On a dry day during the dry season, not less than once a year (Earthing in service).

  6. List the conditions that come before a permit to work is issued.
    Answer 6

    The circuit is isolated from all sources of energy, de-energised and earthed, with local earths at the zone of work and the circuit confirmed dead (Switching operations and the permit to work).

Sources

[1]CEA Safety Regulations 2023, Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023.

[2]CEA standard specification for transformers and reactors, Standard Specifications and Technical Parameters for Transformers and Reactors (66 kV & above voltage class).

[3]IS 3043:1987, Code of Practice for Earthing.

[4]RUS Bulletin 1724E-300, Design Guide for Rural Substations.

[5]FIST 3-30, Facilities Instructions, Standards, and Techniques, Volume 3-30: Transformer Maintenance.

[6]FIST 3-16, Facilities Instructions, Standards, and Techniques, Volume 3-16: Maintenance of Power Circuit Breakers.

[7]FIST 4-1B, Facilities Instructions, Standards, and Techniques, Volume 4-1B: Maintenance Scheduling for Electrical Equipment.

[8]IEC 60050-441, International Electrotechnical Vocabulary, Part 441: Switchgear, controlgear and fuses.

Reference topics explain the methods of the standards for study. For a design, apply the standards and regulations in force.

CitationSubstationLayout Reference, Operation and maintenance, revision 3, 9 Nov 2026, https://substation.solarlayout.app/library/reference/operation-and-maintenance