The substation design process

A substation is designed in a sequence of decisions. The inputs fix the site, the grid connection, the plant and the standards. The single-line diagram fixes the circuits and their equipment. The calculations size the equipment and the earthing, and check the insulation, the clearances, the lightning protection and the auxiliary supply. The layout places the equipment on the site, and the documents record the result for the parties who build it. This topic follows that sequence, names the parties to a substation project, and shows how the design steps of SubstationLayout follow it.

Before this topic: Substations in the power system · Types of substation

1The sequence of the design

The design moves from the inputs to the issued documents. Figure 1 shows the order. Each stage uses the results of the stages before it, and the calculations and the layout depend on one another.

Figure 1.The design process from the inputs to the documents. The calculations and the layout depend on one another: the clearances set the yard, and the lightning protection is placed over it. The drawing is schematic and not to scale.

The International Finance Corporation (IFC) is a member of the World Bank Group, a development institution focused on the private sector in emerging markets. Its guide for utility-scale solar plants lists the electrical designs a project prepares. They are the overall single-line diagrams, the medium-voltage (MV) and low-voltage (LV) switchgear diagrams, the protection systems, the interconnection to the grid, the auxiliary power requirements and the control systems (IFC §2.6.1.1). The same clause states that the design criteria should be set by the national standards and the site's constraints, for example its geotechnical conditions.

2The inputs

The inputs of a design fall into 4 groups.

  • The site: its location, its altitude and air temperature, and the resistivity of its soil. The altitude corrects the clearances, and the soil sets the earth mat (Soil resistivity and Wenner readings).
  • The grid connection: the substation's voltage level, its lines to the grid, and the fault level of the grid at the point of connection. A grid connection permit normally specifies the point of connection and confirms its voltage level, and the application goes to the transmission or distribution utility (IFC §8.2.5).
  • The plant: its type and its capacity, which set the transformers and the MV feeders of a pooling substation.
  • The standards set: the standards and regulations the design follows, which set the voltage levels, the ratings, the clearances and the methods of calculation (The IEC + CEA / CBIP set, The ANSI / IEEE set).

The grid company sets technical requirements for a plant's connection in its grid code. The IFC guide lists limits on harmonics, flicker and frequency, reactive power export, voltage regulation, fault level and system protection among them (IFC §7.4.3). Large substations may need to be designed and built to the grid company's requirements and to the specifications of the interconnection agreement (IFC §7.4.2.4).

3The single-line diagram

The single-line diagram (SLD) is the first drawing of the design. It shows the substation's circuits with one line for the 3 phases. It fixes the bus scheme, the bays and their switching devices, the transformers and the instrument transformers (Single-line diagram (SLD), Bus schemes). The ratings printed on the SLD come from the voltage level and the calculations, and the calculations take their network from the SLD.

4The calculations

The calculations size the equipment and check the design against the standards. Several of them concern faults. A fault, or short circuit, is an accidental connection between phases or between a phase and earth, and the fault current is the large current that flows into it (Faults and fault current, What a fault is). An earth fault, from a phase to earth, drives current into the earth mat, the grid of conductors buried under the yard. A person in the yard during an earth fault can bridge a voltage between the hands and the feet, the touch voltage, or between the feet, the step voltage (Tolerable body current). The design fault level of a voltage level is the fault current its switchgear is rated to carry, and the earth mat is designed for it as its design current (Faults and fault current, Why the fault level matters).

Each calculation answers a question about the substation:

CalculationWhat it givesTopic
Short circuitThe fault currents at the buses, which the switchgear ratings must be at or above, and the earth fault current, which the earth mat's design current must be at or aboveShort-circuit currents by IEC 60909-0
EarthingThe earth mat that keeps the touch and step voltages within their tolerable limits during an earth faultMesh voltage and touch voltage
Insulation and clearancesThe insulation levels of the equipment and the distances in air around the live partsInsulation levels, Electrical clearances
Lightning protectionThe masts and shield wires that protect the yard from direct strokesDirect stroke shielding by the rolling sphere
Auxiliary supplyThe auxiliary transformers, the standby generator, and the batteries and chargers of the direct current (DC) systemAC auxiliary supply

The order of the calculations follows their dependencies. The earth mat is designed for the high-voltage (HV) level's design fault level and for the soil's resistivity from the site. The short-circuit study then calculates the earth fault current from the network and checks that the mat's design current is at or above it. The lightning protection needs the layout of the yard, and the layout needs the clearances.

5The layout

The layout places the bays, the transformers, the buildings, the roads and the fence on the site. The clearances and the bus scheme set the widths and lengths of the bays (Yard layout). The IFC guide states that the layout of a substation should use its space well, comply with the building codes, and keep a safe working space around the equipment (IFC §7.4.2.4). The earth mat and the lightning protection are designed over the layout.

6The documents and the bill of materials

The design ends in documents: the drawings, the calculation reports and the bill of materials (BOM). The drawings show the SLD, the layout, the sections, the earth mat and the lightning protection. The reports record each calculation with its inputs, its equations and its results. The BOM lists the equipment and materials with their specifications and quantities (Bill of materials). Each document carries a number and a revision, and an issued revision records the design as it was sent to the parties (Document control).

7The parties to a project

Several parties take part in the design of a substation. The IFC guide describes their parts for a utility-scale solar plant and its substation:

  • The owner, or developer, finds the site, obtains the permits, secures the power purchase and interconnection agreements, arranges the financing, and selects the team that designs and builds the plant (IFC §2.1).
  • The transmission utility plans and develops the transmission network to which the substation connects, in India the Central Transmission Utility for the inter-State system and a State Transmission Utility for the intra-State system (Substations in the power system, The substation in the power system).
  • The consultant, engaged as the owner's engineer, writes the technical scope of the contracts, supports the procurement and checks the design. The same firm usually follows the construction for the owner (IFC §2.4).
  • The engineering, procurement and construction (EPC) contractor takes full responsibility to complete the project on time, within budget and to the specified performance (IFC §1.2). It prepares the detailed design, buys the equipment to the agreed specifications, builds the plant, carries out the acceptance tests and hands the plant over to its owner (IFC §2.6).
  • The equipment suppliers design, test and deliver the equipment. Large transformers are built to order, with lead times that the IFC guide places in the order of years (IFC §7.4.2.3).

The owner can also manage several contracts in place of one EPC contract (IFC §1.2).

8In the design

SubstationLayout follows the same sequence. The Define pages hold the inputs: Plant & grid, HV switchyard, the MV system, Site & soil, and Protection, where the earth mat's protection basis is entered. The standards set is chosen on the first page, before the HV level that it sets. A new project is the pooling substation of a 250 MW Solar PV plant at 220/33 kV, in the IEC + CEA / CBIP set.

Run design calculates the design from the inputs. It runs the yard layout, the lightning protection, the earthing, the short circuit and the auxiliary supply, in that order. The design steps then show the results: the single-line diagram, the yard layout, the 3D model, the earthing, the short circuit, the lightning protection, the auxiliary supply, the bill of materials and the compliance checklist. The Deliver page lists the files of a revision with their document numbers, and issues the revision.

SubstationLayout designs the substation's primary equipment, its earthing, its lightning protection and its auxiliary supply. It does not set protection relays, route cables or design foundations.

Review questions
  1. List the inputs of a substation design.
    Answer 1

    The site, the grid connection, the plant and the standards set (The inputs).

  2. Explain how the short-circuit study checks the earth mat.
    Answer 2

    The earth mat is designed for the HV level's design fault level, and the short-circuit study checks that this design current is at or above the calculated earth fault current (The calculations).

  3. Name the drawing that fixes the bus scheme, the bays and the transformers.
    Answer 3

    The single-line diagram, the first drawing of the design (The single-line diagram).

  4. Describe the part of the EPC contractor in a project.
    Answer 4

    It takes full responsibility to complete the project, prepares the detailed design, buys the equipment, builds the plant, carries out the acceptance tests and hands it over to the owner (The parties to a project).

  5. State the order in which Run design calculates the steps.
    Answer 5

    The yard layout, the lightning protection, the earthing, the short circuit and the auxiliary supply (In the design).

Sources

[1]IFC, Utility-Scale Solar Photovoltaic Power Plants: A Project Developer's Guide.

Reference topics explain the methods of the standards for study. For a design, apply the standards and regulations in force.

CitationSubstationLayout Reference, The substation design process, revision 3, 9 Nov 2026, https://substation.solarlayout.app/library/reference/how-a-substation-is-designed