Testing and commissioning of substation equipment

A substation's equipment is tested at the factory, again on site after erection, and once more as a whole before it is energised. The factory tests prove the design and the build of each unit. The site tests prove that the unit arrived and was erected without damage, and they record the values that later tests are compared with. This topic explains the tests of the main equipment: the power transformer, the circuit breaker, the instrument transformers and the earth mat. It gives each test's purpose and the criteria its source states, and closes with the sequence that energises a new transformer.

Before this topic: Power transformers · Circuit breakers · Grid resistance and GPR

1Factory, site and commissioning tests

Tests of substation equipment serve at least 3 functions. They prove the integrity of a piece of equipment at its acceptance, verify at intervals that it remains available, and help find the repair a failed unit needs (RUS Bulletin 1724E-300 §19.1). This topic covers the first function, from the factory to energisation. Operation and maintenance covers the periodic tests and those after a failure.

The tests at the factory are of 2 kinds. A type test is made on one unit of a design, to prove that the design meets its standard. A current transformer (CT) specification, for example, requires the type test reports of the offered design from a government or accredited laboratory (KSEB CT specification §8). A routine test is made on each unit before it leaves the factory. Each CT is subjected to routine tests prior to dispatch, in the purchaser's presence if desired (KSEB CT specification §8).

The tests on site follow the erection. Acceptance tests are performed after the receipt and erection of the equipment at the site. Their results are compared with the specifications, with acceptable norms and with the factory test data, and recorded (RUS 1724E-300 §19.2.1). The CEA standard specification for transformers and reactors calls the same stage the pre-commissioning tests. They are made once oil filling is complete, and check the unit's healthiness before it is energised (CEA specification Ch. 5 §12.0).

In the IEC + CEA / CBIP set, the regulations make the site tests a condition of service. No new apparatus, cable or supply line above 650 V is commissioned unless it has been subjected to site tests as per the relevant standards (CEA Safety Regulations 2023, Reg. 48(2)). The manufacturer's certificates of the type, acceptance and routine tests are produced, if required, for the Electrical Inspector's inspection of the installation (Reg. 48(1)). The factory can test at all voltages, while the testing options at site are more limited (CEA specification Ch. 6 §1.0), so the site tests compare low-voltage measurements with the factory values.

2Insulation resistance and the polarisation index

The insulation resistance test is the simplest test of an insulation and the most widely used. A direct voltage from an insulation tester is applied between a winding and the earthed tank, and the resistance is read. The test reveals the dryness of the paper insulation, contaminants in the oil and gross defects inside the tank (CEA specification Ch. 6 §2.4). The specification uses a 2.5 kV tester for windings of 11 kV and above, and preferably a 5 kV tester for extra-high-voltage units. The readings are taken between the windings together and the tank, and between each winding and the tank with the others earthed. The neutral is disconnected from earth first.

The reading rises with the time the voltage is applied, because the insulation draws capacitive and absorption currents that diminish with time, besides its leakage current. Dry insulation shows a marked rise, and wet insulation a small one, since the leakage current grows faster with moisture than the absorption current does (CEA specification Ch. 6 §2.5). The resistance is therefore read at 15 s, 1 min and 10 min, with the oil temperature recorded (CEA specification Ch. 6 §2.4). The readings give 2 ratios. The dielectric absorption index is the ratio of the 60 s to the 15 s reading. The polarisation index (PI) is the ratio of the 10 min to the 1 min reading:

(1)
CEA specification Ch. 6 §2.5
where
polarisation index
insulation resistance read 10 min after the test voltage is appliedΩ
insulation resistance read 1 min after the test voltage is appliedΩ

A ratio has the advantage that the temperature and humidity, which change a single reading, are the same for both of its readings (CEA specification Ch. 6 §2.5). The CEA specification considers a PI above 1.25 and a dielectric absorption index above 1.3 generally satisfactory, when the other low-voltage tests are in order. A PI below 1 calls for immediate corrective action (CEA specification Ch. 6 §2.5). Its minimum 1 min insulation resistance at 30 °C at commissioning is 1500 MΩ for a winding of 66 kV and above, unless the manufacturer recommends otherwise (CEA specification Ch. 6 §2.4). In the ANSI / IEEE set, RUS 1724E-300 §19.3.4.2 grades the same 10 min to 1 min ratio from dangerous below 1 to excellent above 4.

3Dissipation factor and capacitance

An insulation under an alternating voltage acts as a capacitor with losses. The capacitance and the dissipation factor, or loss factor , are measured together with a test set at a voltage below the insulation's withstand. The dissipation factor indicates chemical deterioration with time and temperature, contamination by water, carbon or dirt, leakage through cracks and over surfaces, and ionisation (CEA specification Ch. 6 §2.6). An increase of with a marked increase in capacitance usually indicates excess moisture. An increase of alone may come from thermal deterioration or a contaminant other than water.

The CEA specification takes 0.005 as the maximum of oil-impregnated paper insulation. A rate of change of more than 0.001 per year needs further investigation, and the capacitance may vary between +10 % and −5 % (Ch. 6 §2.6). A condenser bushing is tested through its test tap, in the ungrounded specimen mode, at a voltage not above half its power-frequency test voltage or 10 kV, whichever is lower (CEA specification Ch. 6 §2.7). Its does not exceed 0.005 at first charging, and does not deviate from its initial value by more than 0.001. Its main capacitance stays within 5 % of the factory value (CEA specification Ch. 6 §2.7).

The measurement is sensitive to the surroundings. The porcelain is cleaned and dried, the test is not made with condensation on it, and preferably not above 75 % relative humidity (CEA specification Ch. 6 §2.7). A bushing is not tested in its wooden crate or lying on wood, since wood is a poorer insulator than porcelain and changes the reading (CEA specification Ch. 6 §2.7; FIST 3-30 §4.1.8). The ANSI / IEEE set's sources measure the same losses as the insulation power factor, in per cent. RUS 1724E-300 §19.3.2 compares the acceptance values with those of similar equipment and with the factory values, and later values with earlier ones to find a trend.

4Tests of a power transformer

A transformer's site tests check its windings, its tap changer and its core against the factory's results. The pre-commissioning list of the CEA specification includes the insulation resistance with its PI, the tests on the bushing CTs, and the polarity and vector group. It also includes the ratio on all taps, the magnetising current, the magnetic balance, and the capacitance and of windings and bushings (CEA specification Ch. 5 §12.0). It ends with the frequency response, the short-circuit impedance, the contact resistance, the resistance of all windings on all taps and the earth pit resistance.

Ratio. The turns ratio is checked on each tap, which also proves the alignment and operation of the tap changer. The ratio is within 0.5 % of the nameplate value (CEA specification Ch. 6 §2.2). Shorted turns change the ratio, and out-of-tolerance readings with a high excitation current are symptomatic of them. A transformer turns ratio meter works at a low voltage, so the test can be made with the oil removed (CEA specification Ch. 6 §2.2). RUS 1724E-300 §19.3.15 makes a polarity test on power and instrument transformers after installation, and after any replacement of a unit.

Magnetising current. A single-phase voltage applied to each phase of the high-voltage winding, with the other windings open, draws the current that magnetises the core. Unequal currents indicate a possible short circuit in a winding. Similar single-phase units agree within 10 %, and results agree with earlier tests under the same conditions within 25 % (CEA specification Ch. 6 §2.3). Residual magnetism distorts the reading, so this test comes before the direct-current measurement of the winding resistance (CEA specification Ch. 6 §2.3).

Winding resistance. The resistance of each winding is measured to find loose connections, broken strands and high contact resistance in the tap changer. It is measured with a micro-ohmmeter or a Kelvin bridge below 1 Ω, and compared with the factory value after correction to 75 °C (CEA specification Ch. 6 §2.1):

(2)
CEA specification Ch. 6 §2.1
where
winding resistance corrected to 75 °CΩ
winding resistance measured at the winding temperature Ω
winding temperature at the measurement°C

The expected deviation in the field is 5 % of the factory value (CEA specification Ch. 6 §2.1). FIST 3-30 §4.7.1 gives the same 5 % criterion and the same correction, with a constant of 234.5 °C for copper and 225 °C for aluminium in place of 235. The winding temperature is the uncertain term, so the specification measures when the top and bottom oil temperatures differ by 5 °C or less (CEA specification Ch. 6 §2.1).

Short-circuit impedance. One winding is short-circuited and a low voltage applied to the other. The measured impedance voltage stays within 3 % of the nameplate impedance. A larger variation indicates winding movement from a heavy fault current or from damage in transport, and needs investigation (CEA specification Ch. 6 §2.8).

5Sweep frequency response analysis

A winding that moves under the forces of a short circuit, or in transport, changes its inductance and capacitance. Sweep frequency response analysis (SFRA), which the CEA specification also calls frequency response analysis, detects such a change (CEA specification Ch. 1 para 14, Ch. 6 §2.12). A sinusoidal signal whose root-mean-square value (RMS) is approximately 2 V to 24 V is applied to one end of a winding over a range of frequencies. The response is measured at the winding's other end, both voltages with respect to the earthed tank (CEA specification Ch. 6 §2.12). The result is plotted as the logarithmic ratio of the output to the input voltage, in dB, against frequency. Its resonances and anti-resonances are set by the winding's electrical characteristics.

The response is a signature of the winding, and it is read by comparison. A deformation of a winding or the core cannot be detected by the dissolved gas analysis, the winding resistance or the capacitance and (CEA specification Ch. 6 §2.12). The transformer is completely de-energised and isolated, its bushings are disconnected from the network, and the tap position, oil level and temperature are recorded so that a later test can repeat the conditions. The CEA specification requires that utilities record the pre-commissioning results and the later site results, and analyse their trend (Ch. 1 para 14).

6Tests of a circuit breaker

A circuit breaker's site tests check its contacts and its operating mechanism. Circuit breakers, Operating mechanisms explains the mechanism and its operating times. In a transmission utility's specification, the pre-commissioning tests of the switchyard equipment follow the utility's own procedure, with the test results submitted in its formats (POWERGRID switchyard erection specification §19.1).

Contact resistance. A direct current is injected through the closed contacts, and the resistance across them is measured. FIST 3-16, of the ANSI / IEEE set, uses a current of at least 100 A and takes the manufacturer's limit as its criterion. Where that limit is not available, the resistance does not exceed 200 % of the factory test data. Where neither exists, no pole exceeds the lowest pole's value by more than 50 % (FIST 3-16 §2.4). RUS 1724E-300 §19.3.6.2 gives 50 µΩ to 350 µΩ as the typical range of a high-voltage breaker, and refers to the manufacturer's maximum.

Timing. The timing of a close operation runs from the energising of the close coil to the first touch of the contacts. The timing of an open operation runs from the energising of the trip coil to the separation of the contacts (FIST 3-16 §2.5). The test includes a close, an open and a close-open operation, and adds an open-close and a close-open-close where the breaker recloses. FIST 3-16 keeps the times within the manufacturer's limits, and the poles of most breakers within 2 ms of each other (§2.5). RUS 1724E-300 §19.3.11 makes the timing test at acceptance and after any adjustment or replacement of contacts, to verify that the poles operate simultaneously.

7Tests of instrument transformers

A CT specification lists the routine tests at the factory: the verification of the terminal markings and the power-frequency withstand of the primary and secondary windings. The list continues with the partial discharge of the primary, the inter-turn voltage test, the errors of the measuring and protection cores, and the (KSEB CT specification §9). For its class PS core (class X in the specification's list) it adds the knee point voltage, the exciting current and the secondary winding resistance, the quantities of Current transformers, Saturation and its effect on protection.

In the ANSI / IEEE set, the polarity of each CT and voltage transformer (VT) is tested after installation and after any replacement (RUS 1724E-300 §19.3.15). The turns ratio test is made periodically, to detect turn-to-turn short circuits (RUS 1724E-300 §19.3.14). The excitation test of a CT measures its excitation curve on site, the curve of its secondary voltage against its exciting current. FIST 4-1B makes it upon commissioning and at intervals of 10 years (FIST 4-1B §34.2.2).

The secondary circuits are checked with the primary tests. The CEA specification requires that the unused secondary cores of the bushing CTs be shorted. The star point of the CT secondaries is formed and earthed at one end only, as per the scheme (the checks of CEA specification Ch. 5 §12.0). An open CT secondary under load carries a dangerous voltage (Current transformers, The open secondary). FIST 4-1B §34.2.1 specifies that the secondary wiring be checked for integrity after any work that may have disturbed it.

8The earth mat: the fall-of-potential test

The earth mat's resistance is measured once it is laid and connected, and it is compared with the design's value. The commissioning checks of a transmission utility's station earthing include the soil resistivity, the continuity of the grid's conductors, the weld joints, and the earth resistance of the entire grid and of its sections (POWERGRID switchyard erection specification §19.3). In the ANSI / IEEE set, the value measured on a new installation is compared with the design criteria values (RUS 1724E-300 §19.3.20).

The test is made by the fall-of-potential method of IS 3043. A measured current is passed between the electrode under test and an auxiliary current electrode. The potential difference between the electrode under test and an auxiliary potential electrode is measured, and the resistance is (IS 3043:1987 §37.1). A test at 50 Hz needs a voltmeter whose resistance is high compared with that of the potential electrode, and not less than 20 000 Ω (IS 3043:1987 §37.1.1). The source is isolated from the supply by a double-wound transformer (IS 3043:1987 §37.1.2). Stray currents in the soil make the reading wander, and they are hard to eliminate when the test current has their frequency (IS 3043:1987 §37.1.1, note).

IS 3043 places the electrodes by the size of the electrode under test. For a rod, pipe or plate, the current electrode stands at least 30 m away and the potential electrode midway between them (IS 3043:1987 §37.1.5). The electrodes are placed so that each is independent of the resistance area of the others (IS 3043:1987 §37.1.5). Figure 1 shows the arrangement and the reason. Current flowing from the electrode under test into the soil raises the potential around it, and current entering the current electrode lowers the potential around it. A potential electrode inside either region reads part of the other electrode's potential.

The method may not give satisfactory results for a test electrode of 1 Ω or less, which applies particularly to the combined resistance of large installations (IS 3043:1987 §37.2.1). An earth mat of a substation is such an installation. The alternative method of §37.2.2 finds the electrode positions by trial:

  1. Choose 2 directions at least 90° apart. Lay the potential lead in one, with its electrode 250 m to 300 m from the fence, and the current lead in the other, with its electrode at the same distance.
  2. Take a reading, then move the current electrode out in 30 m steps until 3 consecutive locations give the same reading.
  3. Leave the current electrode in its last position, and move the potential electrode out in 30 m steps until 3 consecutive readings do not change. The last reading is the earth resistance.
Figure 1.The fall-of-potential test of an earth electrode, drawn with the 2 auxiliary electrodes in one line. The tester passes the current between the electrode under test and the current electrode, and reads the voltage to the potential electrode, which stands clear of the regions around both. The drawing is schematic and not to scale.

The physics behind the placement is the subject of IEEE Std 81, the ANSI / IEEE set's guide for measuring the impedance of a grounding system to remote earth. A maker's application note gives its rule. In uniform soil with hemispherical electrodes in one line, the reading equals the electrode's own resistance where the potential electrode stands at the distance that solves (Metrel, Earth resistance measurement and the 62 % rule):

(3)
Metrel application note Eq. 1
where
distance from the centre of the earthing system under test to the current electrodem
distance from the centre of the earthing system under test to the potential electrodem

Multiplying by gives , which reduces to . Its positive root is , or 61.8 % of , the 62 % rule. The model holds where the current electrode stands at least 5 times the diameter of the earthing system away (Metrel, the 62 % rule). It explains why IS 3043's trial positions converge.

Example 1Earth resistance test of the default 220 kV mat

Given: the default project's earth mat of 189.2 m by 133.4 m, 1.5 m outside a fence of 186.2 m by 130.4 m, with a design grid resistance of 0.4310 Ω (Grid resistance and GPR, Example 1).

Method. The design resistance of 0.4310 Ω is at or below the 1 Ω of IS 3043:1987 §37.2.1, so the test follows the alternative method of IS 3043:1987 §37.2.2.

Directions. The potential lead runs out across one side of the fence, along the mat's longer axis, and the current lead across an adjacent side, 90 ° from it.

Potential electrode. It starts 250 m to 300 m from the fence. With 93.1 m from the mat's centre to that side of the fence, it stands 343.1 m to 393.1 m from the centre.

Current electrode. It starts at the same distance from the fence. With 65.2 m from the centre to that side, it stands 315.2 m to 365.2 m from the centre.

Result: Each electrode then moves out in steps of 30 m, the current electrode first, until 3 consecutive readings agree, and the last reading is compared with the design resistance of 0.4310 Ω.

The measured value seldom equals the design's. The design's value rests on a resistivity measured on one day and multiplied by a season factor (Soil resistivity and Wenner readings, The design value). IS 3043 keeps records of the initial resistance of a substation's earth electrodes and of the later tests (IS 3043:1987 §34.4.1). The commissioning measurement is therefore the first entry of that record, against which the periodic tests of Operation and maintenance, Earthing in service are read.

9Commissioning and energisation

Commissioning brings the tested equipment into service as one installation. The CEA specification's checks before the pre-commissioning tests of a transformer include its fittings against the general arrangement drawing and the oil levels in the bushings and conservator. They also include the operation of the Buchholz relay, the pressure relief device and the temperature alarms and trips (CEA specification Ch. 5 §12.0). The final checks before energisation compare the pre-commissioning results with the factory results (Ch. 5 §13.0(a)). They also confirm that the neutral is earthed to 2 separate earth pits connected to the main earth mat (§13.0(f)), and that the phases match the switchyard's buses (§13.0(h)).

The protection is checked with the equipment it protects. The final checks review the transformer's protection scheme with the overall scheme in the control room (Ch. 5 §13.0(s)). The scheme includes the differential, restricted earth fault, overcurrent, earth fault and overfluxing protections, and the oil and winding temperature alarms and trips. Transformer protection explains these protections. RUS 1724E-300 §19.3.16 tests each protective relaying scheme as a whole, with actual abnormal conditions simulated.

The CEA specification energises a new transformer in steps (Ch. 5 §14.0):

  1. Take a dissolved gas analysis of the oil before commissioning.
  2. Charge the transformer on no load, and observe it continuously on no load for at least 24 hours.
  3. Put it on load gradually, and check the temperature rise against the load, the vibration, oil leaks, oil levels, the gas detector relay and the noise.
  4. Check the tap changer's operation.
  5. Scan the high-voltage and low-voltage terminals and the tank with a thermal imaging camera, once the unit is stable above 60 °C.
  6. Repeat the dissolved gas analysis after 24 hours, 1 week, 15 days, 1 month and 3 months, and then at the normal interval of 6 months.

Operation and maintenance, Dissolved gas analysis of transformer oil explains the dissolved gas analysis, and Construction sequence and erection, Cabling, surfacing and handover the Electrical Inspector's inspection before supply commences. The contractor hands the testing and commissioning records to the operation staff for future reference (CEA specification Ch. 5 §14.0).

10In the design

SubstationLayout specifies no test and sets no relay. It gives the values that the tests are compared with, and lists the test requirements on the compliance checklist.

Earth mat. The earthing step gives the mat's grid resistance, 0.4310 Ω for the default project, against which the test of Example 1 is compared. The value assumes the design resistivity of 150 Ω·m (Grid resistance and GPR, In the design). A site measurement that differs from it can come from the soil as well as from the mat.

Transformer. The interconnecting transformer (ICT) of the default project is rated 160 MVA, 220/33 kV, YNyn0, with an impedance of 12.5 %. Its on-load tap changer (OLTC) has a range of ±10 % in steps of 1.25 %. The ratio, vector group and short-circuit impedance tests check these values, the impedance within 3 % (Tests of a power transformer). The IEC checklist has an item for the ICT's routine, type and special tests, impedance and losses as specified (IEC 60076-1:2011). The IEEE and ANSI checklist of the ANSI / IEEE set has an item for the power transformers' ratings, tests and impedance (IEEE C57.12.00).

Instrument transformers. The high-voltage (HV) CT of the default project is 1600-800/1 A, with 5 cores, 0.2S, 0.2S, 5P20, 5P20, PS (Current transformers, In the design). Its class PS core takes the added routine tests of Tests of instrument transformers. The capacitor voltage transformer (CVT) has the secondaries 0.2, 3P, open delta.

Electrical Inspector. The CEA / Indian checklist has an item for the electrical inspector's consent to energise the installation (CEA Safety Regulations 2023, Reg. 45(3), 45(4)). It has no automatic check, and it reads Needs your answer until the user answers it.

Review questions
  1. Distinguish a type test from a routine test.
    Answer 1

    A type test is made on one unit of a design to prove the design, and a routine test is made on each unit before it leaves the factory (Factory, site and commissioning tests).

  2. Explain why the polarisation index is insensitive to the temperature of the insulation.
    Answer 2

    Both of its readings, at 10 min and at 1 min, are taken at the same temperature and humidity, so the ratio cancels their effect (Insulation resistance and the polarisation index).

  3. State what an increase of the dissipation factor with a marked increase of the capacitance indicates.
    Answer 3

    It usually indicates excess moisture in the insulation (Dissipation factor and capacitance).

  4. Give the timing criteria of a circuit breaker's poles in FIST 3-16.
    Answer 4

    The times stay within the manufacturer's limits, and the timing between the phases does not exceed 2 ms for most breakers (Tests of a circuit breaker).

  5. Derive the 62 % rule of the hemispherical-electrode model.
    Answer 5

    The equation of Eq. (3) reduces to , whose positive root places the potential electrode at 61.8 % of the distance to the current electrode (The earth mat: the fall-of-potential test).

  6. List the steps that energise a new transformer.
    Answer 6

    A dissolved gas analysis, a charge on no load observed for at least 24 hours, gradual loading with checks, the tap changer and a thermal scan, then further gas analyses at set intervals (Commissioning and energisation).

Sources

[1]CEA standard specification for transformers and reactors, Standard Specifications and Technical Parameters for Transformers and Reactors (66 kV & above voltage class). §2.5; §2.1.

[2]CEA Safety Regulations 2023, Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023.

[3]IS 3043:1987, Code of Practice for Earthing.

[4]Metrel application note, Application note: Earth resistance measurement and the 62 % rule. Eq. 1.

[5]IEEE Std 81-2012, IEEE Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Grounding System.

[6]POWERGRID switchyard erection specification, Technical Specification, Section: Switchyard Erection.

[7]KSEB CT specification, Technical Specification: 220 kV & 110 kV Current Transformers (Live / Dead Tank Type) of Various Ratings and Supporting Structures.

[8]RUS Bulletin 1724E-300, Design Guide for Rural Substations.

[9]FIST 3-30, Facilities Instructions, Standards, and Techniques, Volume 3-30: Transformer Maintenance.

[10]FIST 3-16, Facilities Instructions, Standards, and Techniques, Volume 3-16: Maintenance of Power Circuit Breakers.

[11]FIST 4-1B, Facilities Instructions, Standards, and Techniques, Volume 4-1B: Maintenance Scheduling for Electrical Equipment.

[12]IEC 60076-1:2011, Power transformers, Part 1: General.

[13]IEEE C57.12.00, IEEE Standard for General Requirements for Liquid-Immersed Distribution, Power, and Regulating Transformers.

[14]IEC 60050-441, International Electrotechnical Vocabulary, Part 441: Switchgear, controlgear and fuses.

Reference topics explain the methods of the standards for study. For a design, apply the standards and regulations in force.