Site, survey and environmental considerations

A substation's site fixes much of its cost and its performance before the first drawing is made. The site determines the length of the lines that reach it, the earthwork that levels it, the foundations its soil can carry, and the water that drains across it. It also determines how near the substation stands to its neighbours. This topic explains how a site is chosen, the surveys that describe it, and the drainage, flooding, access and environmental questions that the design of the site answers. The sources of each standards set are given with their own practice.

Before this topic: Yard layout · Soil resistivity and Wenner readings

1Site selection

The location and siting of a substation are among the most critical factors of its design (RUS Bulletin 1724E-300 §2.2). A poor choice leads to excessive investment in substations and in the lines that serve them. RUS 1724E-300 also advises an initial investigation of the site before the property is bought. A former dumping ground, for example, may hold buried material or toxic waste that must be removed before grading.

The factors RUS 1724E-300 lists fall into groups (§2.2):

  • The power system. The present and future load centre and sources of power, the right-of-way for the overhead or underground lines, and the existing distribution lines.
  • Access. An all-weather highway and a railway siding nearby, and access for heavy equipment in all weather (Access).
  • Land. Space for the future as well as the present, the land title, zoning and ordinances, and the topography of the site and its surroundings. Earthquake fault lines, floodplains, wetlands and prime farmland are avoided where possible.
  • Soil. The soil resistivity, the drainage and soil conditions, the cost of earthmoving, and the cost of cleaning up contaminated soil.
  • Environment and the public. Objections to appearance, noise or electrical effects, public safety, distance from schools and playgrounds, threatened species and cultural resources, and salt or industrial contamination of the air.
  • Security. Protection from theft, vandalism, sabotage and the weather.

Space for the future matters because a substation grows. RUS 1724E-300 recommends that the designer plan for the ultimate requirements as well as the initial ones, and compare the cost of the provisions that make additions easy (§2.1). The site is also chosen so that no communications facility stands within the station's 300 Vp ground potential rise (GPR) zone of influence (RUS 1724E-300 §2.2).

2Topographic survey and grading

The design of the site begins with the survey of its surface. RUS 1724E-300 recommends that the engineer inspect the site in person before the design starts, and use the natural drainage and topography in the design (§6.1). Its preliminary requirements are these (RUS 1724E-300 §6.3):

  1. area maps, with aerial photographs where available;
  2. a topographic drawing with ground elevations on a grid at 15 m spacing;
  3. the location and elevation of roads, railways, ditch inverts and culverts, and the exact location and depth of pipelines and other utilities;
  4. the property plan, the drainage exits of the area, the high water elevation, and the flood zone with its base flood elevation;
  5. soil borings in the site area (Geotechnical investigation).

In the IEC + CEA / CBIP set's practice, the contractor clears the site and sets up a grid of coordinates on it. At least 4 masonry or concrete pillars serve as bench marks, connected to a permanent bench mark (OPTCL Technical Specification E-6 §2.2). The clearing avoids soil erosion and water pollution (OPTCL E-6 §2.1).

The survey sets the grading. A flat yard is the most common and the most desirable, because it allows uniform foundation levels and structure heights (RUS 1724E-300 §6.2). A sloped or a stepped yard is used where the property or the rock makes a flat one uneconomical. On a site that is not flat, the yard's level balances the fill of the embankment against the earth cut from the higher ground (RUS 1724E-300 §6.5.3). RUS 1724E-300 takes only 80 % to 85 % of the cut volume as available for fill, to allow for losses in compaction and spillage and for unsuitable material. It keeps the slopes at 1 vertical to 4 horizontal where possible. It compacts the fill in layers of 200 mm to 95 % of the maximum density of the laboratory compaction test of AASHTO T 180 (§6.5.4). The compaction develops the bearing capacity of the foundations and keeps the yard from settling. Figure 1 shows a graded yard in section.

Figure 1.A graded yard in section. The yard is cut on the high side and filled on the low side, it falls gently to its drains, and its level and outfall stand above the high flood level. The drawing is schematic and not to scale.

3Geotechnical investigation

A subsurface investigation is made for each substation, because the foundations' design rests on it (RUS 1724E-300 §8.2.1). RUS 1724E-300 takes the borings at the critical foundations, the deadend structures and the transformers. It takes 3 at a small substation and 6 to 10 at a larger one, to a depth of 10 m below the final grade. Heavier loads, softer or wetter soils and a deeper groundwater level call for deeper borings.

The samples are described by the Unified Soil Classification System (RUS 1724E-300 §8.2.2). The geotechnical engineer decides whether the soil behaves as a cohesive, clay-like soil or as a granular, sand-like soil. Where in doubt, the foundations are designed both ways, and the design that gives the larger foundation is used. Index tests, such as grain size, moisture content and the plasticity limits, confirm the classification. Strength parameters come from undisturbed samples or from tests in place, such as the cone penetrometer, which disturb the soil least (RUS 1724E-300 §8.2.3).

In the IEC + CEA / CBIP set's practice, the investigation is made on the original soil, before any cutting or filling (OPTCL Technical Specification E-6 §3). It covers the critical locations: the control building, the transformers and reactors, the lightning masts and the bay columns (OPTCL E-6 §3.1). Its programme is this (OPTCL E-6 §3.2 to §3.8):

  • at least 5 boreholes of 150 mm diameter to IS 1892, to 15 m or to refusal, with standard penetration tests at intervals of 2 m and the water table recorded in each;
  • undisturbed samples at intervals of 2.5 m and at each change of stratum;
  • dynamic cone penetration tests under the transformers, trial pits, and field California bearing ratio tests on the road lines;
  • a plate load test to IS 1888 for the bearing capacity and settlement at shallow depth;
  • samples of the groundwater, and laboratory tests that include the chemical tests for carbonates, sulphates, nitrates, chlorides, pH and organic matter that attack concrete.

The report gives the bore logs, the test results and the recommendations: the type of foundation for each structure and the allowable bearing pressure at various depths, with the calculations (OPTCL E-6 §3.9). It also comments on the chemical nature of the soil and on any expansive soil found. Structures and foundations, Foundations explains how the foundation design uses these results. A site where an earthquake could liquefy the soil also needs a seismic evaluation by a geotechnical engineer (RUS 1724E-300 §8.2.7).

4Soil resistivity survey

The earth mat's design needs the soil's resistivity, measured on the site by the Wenner method (Soil resistivity and Wenner readings, The Wenner method). The survey has its own practical rules. In the IEC + CEA / CBIP set's practice, the test is made on the original soil, before cutting or filling, at points that cover most of each voltage level's switchyard (OPTCL Technical Specification E-6 §4.0). It is taken preferably from January to April, when the soil is relatively dry, and not within a week of rain. The report records the date, the weather, the ambient temperature and the instrument, and the instrument's calibration is checked before use.

The OPTCL specification requires readings at electrode spacings of 1 m to 15 m in 8 directions from each point. The soil is uniform where the readings vary within 30 %, and the larger value of the locations is the soil resistivity of the substation. Otherwise a two-layer or multilayer model is fitted. The design's own rule for uniformity is in Soil resistivity and Wenner readings, Spacings and uniformity.

5Drainage and flooding

A yard must drain, so its equipment stands dry and its surface stays firm. RUS 1724E-300 specifies drainage sufficient to leave little standing water within a few hours of heavy rain (§2.3.2.5). Most yards drain by surface runoff. In RUS 1724E-300's practice the ground slopes gently, at 0.5 % to 0.75 %, to the yard's edge or to shallow ditches, which discharge to culverts or channels (§6.4.2). A closed system of catch basins and storm sewers is costly and is rarely needed at a rural substation (RUS 1724E-300 §6.4.3).

The drainage is planned with the cable trenches and the roads (RUS 1724E-300 §6.4.4). A good rule is to discharge no more water into an existing outlet than the site discharged before. Many local authorities require detention or retention basins for the stormwater (RUS 1724E-300 §6.4.1). To size a culvert, a pipe or a ditch, RUS 1724E-300 takes the peak runoff by the rational method (§6.4.5):

(1)
RUS Bulletin 1724E-300 §6.4.5, Eq. 6-1
where
peak runoff from the drainage aream³/h
runoff coefficient of the surface
average rainfall intensity for a storm whose duration equals the time of concentrationm/h
drainage aream²

The time of concentration is the time the runoff takes to reach the point under design from the remotest part of the area. RUS 1724E-300 takes a storm frequency of 2 or 5 years and a time of concentration of 15 min to 20 min for a reasonable and economical design. The method is not recommended for drainage areas much larger than 40 ha to 81 ha (100 to 200 acres). In the bulletin's example, an area of 2000 m² with = 0.50 and = 0.094 m/h gives 94 m³/h, or 0.026 m³/s. A pipe is sized for a velocity of at least 1 m/s, so it cleans itself of silt (RUS 1724E-300 §6.4.5).

In the IEC + CEA / CBIP set's practice, open storm water drains run on both sides of the roads. The drains' invert is set so the water discharges above the high flood level, outside the substation's boundary, with pumping where needed (OPTCL Technical Specification E-6 §9.1). The same specification adds rainwater harvesting, recharge structures fed by branches of the main drain (OPTCL E-6 §21.0). The flood level matters for the site's choice as well as its drainage: RUS 1724E-300 avoids floodplains where possible and records the high water and the base flood elevation in the survey (Site selection, Topographic survey and grading).

6Access

The heaviest load that reaches a substation is usually its power transformer, and the access road must carry it. RUS 1724E-300 specifies access roads adequate for heavy equipment in all weather, with culverts and crossings designed for those loads (§6.6.1). Its maximum grade is generally 7 %, so normal movers can haul a transformer, with 10 % tolerated for 60 m to 100 m (RUS 1724E-300 §6.6.2). Its inside radius at a right-angle junction with a major road is at least 15 m, for long vehicles, and RUS 1724E-300 allows smaller radii for its substations below 230 kV (§6.6.3). Where space allows, its road is 6 m wide and crowned for drainage (RUS 1724E-300 §6.6.4).

A railway spur may be economical at some sites, built to the railway company's standards (RUS 1724E-300 §6.6.5). The roads inside the yard are in Roads, trenches and buildings, Roads. In the IEC + CEA / CBIP set, the CEA standard specification makes the transformer's supplier responsible for surveying the route to the site (Power transformers, Transport).

7Environmental and community considerations

A substation must be acceptable to the community around it. RUS 1724E-300 groups the environmental considerations of the ANSI / IEEE set as follows (§2.3.1):

  • Assessment. A substation that disturbs more than 2 ha (5 acres) of new ground generally needs an environmental assessment, and a smaller one an environmental report.
  • Appearance. Screening by landscaping or walls, low-profile designs, solid-shape structures, colours that blend into the background, and outdoor lighting that can be partly switched off at night.
  • Audible noise. The transformers are the main source (Audible noise).
  • Electrostatic and electromagnetic effects. Corona at small radii can interfere with radio and television. It is seldom serious at 230 kV and below, and corona shields are used at 345 kV.
  • Effluent. No harmful quantity of oil may reach a navigable waterway after a container fails (Fire protection and oil containment, Oil retention in the ANSI / IEEE set).

The site's weather also enters the design: the extreme temperatures, the wind, the ice, the rain, the snow, lightning and fog with airborne contamination (RUS 1724E-300 §2.3.2). The altitude lowers the dielectric strength of the air and the cooling of equipment (RUS 1724E-300 §2.3.3). The fence keeps out wildlife and livestock, and clearances protect birds (RUS 1724E-300 §2.3.5). IEEE 1127 is the ANSI / IEEE set's guide for the community acceptance and environmental compatibility of substations.

In the IEC + CEA / CBIP set, the CEA standard specification requires the utility to state the site's service conditions for a transformer or reactor (Ch. 2 §10.0). They are the altitude, the ambient and cooling air temperatures, the seismic zone with its ground acceleration, and the wind zone of the National Building Code's map. The OPTCL specification follows the norms of the State Pollution Control Board under the Water Act for the quality of the effluent from the site (§28.0).

8Audible noise

Among the sources of a substation's noise, the transformers have the greatest potential for objectionable noise (RUS 1724E-300 §2.3.1.4). The others are the voltage regulators, the circuit breakers and corona. Sound spreads radially from its source, and its level falls by approximately 6 dBA with each doubling of the distance (RUS 1724E-300 §5.2.12.1, §5.2.12.3). A low site with homes on the higher ground around it is therefore a poor choice.

RUS 1724E-300 controls the noise in 3 ways. In the choice of the site, it takes the greatest distance from nearby residences and avoids a direct line of sight where possible (RUS 1724E-300 §2.3.1.4.1). Mounds and shrubbery between the source and the public have little effect on the level, but reduce the psychological impact of a new substation (RUS 1724E-300 §5.2.12.2). In the layout, it places the transformers as far from the fence as possible. If noise is expected to be a problem, a quieter transformer or a sound barrier follows (RUS 1724E-300 §2.3.1.4.2). IEEE 1127 gives the formulas for the sound level at a distance. As a general rule, the substation's noise is not a problem when, combined with the ambient noise, it is less than 5 dBA above the ambient level (RUS 1724E-300 §2.3.1.4.3). The ambient level is measured in the quietest period, from midnight to 4 a.m.

In the IEC + CEA / CBIP set, the CEA standard specification limits the noise level of a transformer to the values of its Annexure A (Ch. 2 §5.4). The level is measured with the transformer energised at normal voltage and frequency, with its fans and pumps running.

9In the design

The design does not choose a site or make a survey. It takes the survey's results as inputs and uses them in its steps. The default project's measured soil resistivity is 100 Ω·m. Its season factor of 1.5 gives the design resistivity of 150 Ω·m (Soil resistivity and Wenner readings, The design value). Wenner readings entered from the survey replace the typed value, and the compliance checklist's soil resistivity item is answered from the site survey where the readings are missing.

The input Altitude, 500 m on the default project, increases the yard's clearances above 1000 m. The input Maximum ambient temperature, 50 °C on the default project, enters the size of the earth conductor. The site's latitude and longitude place the sun for the 3D model, and its easting and northing place the model on the map. The design does not grade the yard, design its drainage or assess its noise (Roads, trenches and buildings, Trenches, foundations and drainage in the design).

Review questions
  1. List the groups of factors that govern the choice of a substation site.
    Answer 1

    The power system, access, land, soil, the environment and the public, and security, with space for the future (Site selection).

  2. Explain why only 80 % to 85 % of the cut volume is taken as available for fill.
    Answer 2

    The rest allows for the losses due to compaction and spillage and for unsuitable material (Topographic survey and grading).

  3. State when and where the IEC + CEA / CBIP set's practice makes the geotechnical investigation.
    Answer 3

    On the original soil, before any cutting or filling, at the critical locations: the control building, the transformers and reactors, the lightning masts and the bay columns (Geotechnical investigation).

  4. Calculate the peak runoff of a yard of 2000 m² with a runoff coefficient of 0.50 and a rainfall intensity of 0.094 m/h.
    Answer 4

    By the rational method the runoff is = 94 m³/h, or 0.026 m³/s (Eq. (1)).

  5. Give the rule by which RUS 1724E-300 judges that a substation's noise is not a problem.
    Answer 5

    Its noise, combined with the ambient noise, is less than 5 dBA above the ambient level measured in the quietest period (Audible noise).

Sources

[1]RUS Bulletin 1724E-300, Design Guide for Rural Substations. §6.4.5, Eq. 6-1.

[2]OPTCL Technical Specification E-6, Technical Specification E-6, Civil Works.

[3]CEA standard specification for transformers and reactors, Standard Specifications and Technical Parameters for Transformers and Reactors (66 kV & above voltage class).

[4]IEEE 1127, IEEE Guide for the Design, Construction, and Operation of Electric Power Substations for Community Acceptance and Environmental Compatibility.

[5]IS 1892, IS 1892.

[6]IS 1888, IS 1888.

[7]AASHTO T 180, the laboratory compaction test (modified).

Reference topics explain the methods of the standards for study. For a design, apply the standards and regulations in force.